March 2024
Trial fitting of the steam pipe cladding commenced which identified a few adjustments that are required. The valve mating faces on the...

jameslawrence87
Apr 10, 20241 min read


February 2024
This month has seen some quite notable progress at Project 62. 30075 Locomotive Substantial progress has resulted in us completing the...

jameslawrence87
Mar 8, 20242 min read


January 2024
Despite chilly conditions, the team continued to make notable progress across various aspects of the project. The installation of the...

jameslawrence87
Feb 25, 20242 min read


December 2023
Outside of the shelter, the shillingstone P-way team tirelessly laboured on the installation of new track to connect with the P62 tent....

jameslawrence87
Dec 28, 20231 min read


November 2023
Volunteering always gets more difficult in the winter months, and so we worked on the PMV where we could, to allow ourselves extra indoor...

jameslawrence87
Dec 14, 20231 min read


October 2023
A wet and miserable month - the team continued their works regardless! Structural Adjustments The left-hand side tank was lifted off...

jameslawrence87
Oct 25, 20231 min read


September 2023
September saw our volunteers working through some very wet days! Our team worked on the below; - A trial fit of the balance pipe for the...

jameslawrence87
Oct 9, 20231 min read


August 2023
A busy month, with plenty of preparation for the Shillingstone 160th Birthday event taking place. Work surged ahead to ensure that 30075...

jameslawrence87
Oct 9, 20231 min read