top of page
Search

September 2023

September saw our volunteers working through some very wet days! Our team worked on the below;

- A trial fit of the balance pipe for the side tanks was done, and the balance pipe control valve is now being lapped.

- Various pipework was fitted, including new gaskets for the joints between the balance pipe, side tanks, and feed water pipes to the injectors.

- Fabrication and insulation work on the steam dome were started and later tidied up.

- Work on the fire hole door's shovel protector and smokebox steam pipe blanking plates continued. The firehole door shovel protector was eventually completed.

- Parts for the grate were prepared, and fixing bolts and nuts under the side tanks were serviced.

- Sander outlet pipes were located and prepared for painting, eventually being primed.

- Work on covering plates for the smokebox and steam pipes continued, as well as on blanking plates for the bottom of the smokebox.

- Three pairs of washout plug surrounds for the boiler cladding were cleaned and primed.

- Welding was done on the firebox's bottom plates and some ashpan fittings.



Additional Updates:


- The painting of the PMV is ongoing, boosted by volunteers from "Southern & Scottish Electricity."

- A scaffold tower was erected adjacent to the shelter, and internal tidying of vehicles continued.

- Paul Antell visited to inspect the firebox and agreed to return for welding.







 
 
 

Recent Posts

See All
February 2026

Earlier in the month the boiler washout on 30075 was completed following the internal inspection and flushing through of the boiler. The washout plugs have now been fully reinstated, including those w

 
 
 

Comments


bottom of page