September 2025
Early in the month, attention was split between 30075, 30076, and the eight-plank wagon. On the wagon, painting of the floor plank ends...

jameslawrence87
Oct 42 min read
Â
Â
Â


August 2025
August has been a landmark month for Project 62, with major progress achieved on both the eight-plank wagon and locomotive 30075. The...

jameslawrence87
Sep 102 min read
Â
Â
Â


NEWSFLASH - BACK IN STEAM
Today, on the 6th of August 2025, 30075 finally passed her boiler steam test, and her 10 year certification has now started. Our chairman...

jameslawrence87
Aug 61 min read
Â
Â
Â


July 25
During July work advanced steadily on both the eight-plank wagon and locomotive 30075. On the wagon, painting featured prominently,...

jameslawrence87
Aug 61 min read
Â
Â
Â


June 2025
Efforts on the eight plank wagon focused on continued de-rusting and priming of the chassis, which progressed well over several working...

jameslawrence87
Jul 72 min read
Â
Â
Â


May 2025
Throughout the month, work progressed on both the eight-plank ex-ash wagon and locomotive 30075. On the wagon, fitting and adjustment of...

jameslawrence87
Jun 72 min read
Â
Â
Â


April 2025
April saw consistent progress on both the eight plank (ex-ash) wagon and 30075. Work on the wagon continued steadily, with more derusting...

jameslawrence87
May 41 min read
Â
Â
Â


March 2025
March ended on a positive note as we successfully raised steam on 30075 following weeks of steady preparation. While not a full steam...

jameslawrence87
Mar 312 min read
Â
Â
Â


February 2025
February has been a steady month of progress on both the eight-plank wagon and 30075, with work continuing despite the usual winter...

jameslawrence87
Mar 52 min read
Â
Â
Â


January 2025
Finally, work has been able to start gathering momentum again, given the return of the injector. With its arrival mid-month, attention...

jameslawrence87
Jan 292 min read
Â
Â
Â


November and December 2024
We’re eagerly awaiting the arrival of our injector, which has been promised to us by the end of the year. Progress on 30075 has slowed...

jameslawrence87
Dec 31, 20241 min read
Â
Â
Â


September and October 2024
You may have noticed our posts have been quite thin on the ground in the last few weeks. We are simply waiting for our Injector from our...

jameslawrence87
Oct 21, 20241 min read
Â
Â
Â


August 2024
In all honesty, due to the necessary injector replacement, not a huge amount of progress has taken place in August. Once we receive the...

jameslawrence87
Sep 14, 20241 min read
Â
Â
Â


July 2024
We have during July dealt with the issues we expected to find during steam testing. 1. Cladding and Insulation: - Boiler Barrel and Cab...

jameslawrence87
Aug 3, 20242 min read
Â
Â
Â


June 2024
After the exciting progress made in May, the reality was that various issues were identified during another steam test on the 5th of...

jameslawrence87
Jul 14, 20242 min read
Â
Â
Â


May 2024
For the first time in many years, 30075 had a fire lit and steam raised on the 22nd May, 2024. We will be slowly testing the locomotive...

jameslawrence87
Jun 19, 20242 min read
Â
Â
Â


April 2024
Within the cab of 30075, the fitting of the wooden floor has nearly been completed. Rather symbolically, the whistle was refitted and the...

jameslawrence87
May 6, 20242 min read
Â
Â
Â


March 2024
Trial fitting of the steam pipe cladding commenced which identified a few adjustments that are required. The valve mating faces on the...

jameslawrence87
Apr 10, 20241 min read
Â
Â
Â


February 2024
This month has seen some quite notable progress at Project 62. 30075 Locomotive Substantial progress has resulted in us completing the...

jameslawrence87
Mar 8, 20242 min read
Â
Â
Â


January 2024
Despite chilly conditions, the team continued to make notable progress across various aspects of the project. The installation of the...

jameslawrence87
Feb 25, 20242 min read
Â
Â
Â