December 2025
Earlier in the period, work on 30076 focused on the exhaust manifold area, with all studs successfully removed and the majority of threads cleaned out using a tap, allowing preparation for reassembly to continue. Attention was also given to the mechanical lubricator support frame, which was rubbed down and treated with anti-rust paint, and ongoing work progressed on one of the side tanks to ensure correct clearance around the sander pipework. One of the side tanks was reposit
jameslawrence87
Dec 14, 20252 min read


November 2025
Work across the month focused on preparing 30075 for final presentation and continuing the methodical overhaul of components from 30076. Early in the month the front of the shelter was adjusted to provide the necessary headroom for 30075 to be moved inside, after which flangeways were cleared and the locomotive was positioned under cover. Once secured, attention turned to paintwork, with filling, rubbing down and surface preparation carried out across successive sessions. Tre
jameslawrence87
Dec 6, 20252 min read


October 2025
During October, work continued across locomotives 30075 and 30076 and on the eight-plank wagon, with consistent volunteer attendance and good progress made despite increasingly mixed weather. Early in the month, the wagon floor was completed and corner boards fitted, followed by touch-up painting and lacquer application. A new canopy tarpaulin was fitted mid-month, with seams sealed and bungee cords secured, and both ends received commemorative plaques, including one for Bi
jameslawrence87
Nov 5, 20252 min read


September 2025
Early in the month, attention was split between 30075, 30076, and the eight-plank wagon. On the wagon, painting of the floor plank ends...
jameslawrence87
Oct 4, 20252 min read